Progress continues to be good on the building. The following are some key indicators:
- Structure complete
- Internal walls largely completed levels 1-6 and well on the way to level 7 (top floor)
- Services roughed in to level 7
- Painting commenced on level 1
- Preparation for tiling well advanced levels 1-4
- External finishes well advanced
- Acoustic screen to Anzac Parade commenced
- Power sub station installed
The following photographs give a sense of the progress.
Above: Stockpiling tiles and other materials on the roof
Above: Granisite surfacing well under way (first 2 of 6 coats)
Above: Terrasite finishes commence on northern facade
Above: Main Common Room

External finishing well underway