26 August, 2008
Latest Shots
Lipman is still making good progress on the New College Village. As previously reported the structure is completed. As well:
* Internal walls are now completed for all floors
* Most gyproc internal walls are completed
* Tiling of bathrooms and most fittings are completed to level 1
* Tiling is under way on levels 2 & 3
* Windows are installed to Level 6
* The installation of elevators is well advanced
* Most electrical, mechanical and haudraulic services are finished to Level 7
* External surface finishing is well progressed
* Sealing of the roof is close to completion
14 August, 2008
External finishing well underway
Progress continues to be good on the building. The following are some key indicators:
- Structure complete
- Internal walls largely completed levels 1-6 and well on the way to level 7 (top floor)
- Services roughed in to level 7
- Painting commenced on level 1
- Preparation for tiling well advanced levels 1-4
- External finishes well advanced
- Acoustic screen to Anzac Parade commenced
- Power sub station installed
External finishing well underway
04 August, 2008
Views of the completed structure
As I said in my last post the structure is now completed - all seven floors are erected and the roof has been poured. Fitting out is proceeding at a rapid pace. In summary:
- Internal walls are almost erected to level 6
- Services are roughed in to Level 6
- Painting and tiling have begun on Levels 1 & 2
- External surfaces are well advanced.
Photo 1: View of the northern facade from NIDA
Photo 2: View of the southern facade from the top of the L5 Building at UNSW
Views of the completed structure
Subscribe to:
Posts (Atom)