March was a great month for construction with no days lost due to rain. As a result there has been good progress on site. The last ground floor slab was pouted this week and work on Levels 1 and 2 are well advanced. All of the AFS walls have been erected for Level 1 and 60% of Level 2. With the completion of the missing link slab at ground level we will see the structure rising (eventually) at a uniform rate. The East and Southern sections of the building will continue to be in advance of the west and north for some weeks.
A prototype room is nearing completion, and as well as allowing Lipman to test construction methods and materials, will allow us to show prospective residents what the accommodation will be like.
View of the southern wing across the inner courtyard
View of the southern and western wings and the courtyard
View to the west showing existing western campus buildings
Level 2 takes shape