17 March, 2008

The structure begins to rise


Progress on the building has been good during February and March and hence the structure is beginning to be more obvious on Anzac Parade. The floor slab for Level 2 is beginning to take shape and we should see the first of two major pours tomorrow. Once all of the Level 2 floor has been poured the structure will become more repetitive and faster so we should see even more progress. The following shots give some sense of the progress. The picture above is from the top of the L5 building.

Above - part of the inner courtyard and the walls of Level 1 emerging.


Above - view from the NIDA end of the site looking south.


Above - The Level 2 slab being prepared for the pour.
Share/Bookmark

No comments: