
There has also been good progress on the final pier caps and foundations that are necessary before the non-suspended ground floor slabs are poured.
Some key achievements in the last two weeks have included:
- The piers were completed last week.
- The western elevator pit was poured this week.
- The final bridging caps in the basement area were poured.
- Good progress has been made on the pile caps at the ground floor level.
- The ground floor suspended slab has progressed well and the first section was poured this week with more sections to come soon.
- The New College Big Top (see previous post) has largely been removed with the last of back filling taking place and some sand being trucked off site.



No comments:
Post a Comment