Construction recommenced after the Christmas shut-down on Monday 7th January and since then progress has been good. While the project is still a little behind Lipman has made some changes to the construction program designed to catch up some time. Progress in week 1 after the break has included:
- completion of the concrete piles (by today)
- erection of the crane tower
- commencement of underfloor plumbing
Key milestones in coming weeks include:
- completion of all screw piles this week
- completion second elevator shaft pit
- pouring of first section of basement floor by 21/1/08