15 October, 2008

A building emerges from the scaffolding

I haven't posted photos for s few weeks because most of the obvious progress on the building has been inside. And this progress has been significant. For example:
  • Carpetting up to level 4
  • Furniture being installed
  • Level 7 (last floor) walls completed and fit-out well advanced
  • Kitchens and built-in items largely installed
  • All major services (e.g Air conditioning) virtually completed
Outside the building progress is also good.
  • Balcony rails and awnings are being installed
  • All the facade finishes are well advanced
  • The acoustic screen on Anzac Parade is now being installed
Up to this stage, the outside of the building has been shrouded by the scaffolding; but as it is being slowly removed the beauty and scale of the building are obvious. I have received numerous comments from varied sources about just how good the building looks (well done Lipman and AJC). In the next few weeks the scaffolding will be completely down and the building's quality will be clearer.

The good news is that we are on track for completion before Christmas this year. Our first resident will arrive on January 5th 2009.

Here are some recent images.

Above: Northern elevation viewed from NIDA

Above: Eastern elevation, the acoustic screen is now being installed

Above: The north-eastern elevation from Anzac Parade

Above: Partial view of a studio Kitchenette (sink, cooktop, fridge, microwave)

Above: Bathroom fittings (all 316 bedrooms have a bathroom like this)

Share/Bookmark

No comments: