16 September, 2008

Fit-out well on the way

We are within 12 weeks of completion of the New College Village. Progress has been good on all fronts. Only Level 7 has significant work to be done with most walls completed and services well advanced. On lower floors the extent of the fit-out varies with elevation. Levels 1 and 2 are almost complete with carpet laying to commence in apartments and studios soon. Most kitchens are now fitted up to Level 4 and painting is well advanced on lower levels. Tiling to bathrooms is completed to Level 3 and underway up to Level 6. The rooftop services are also well advanced with air conditioning and hot water units currently being installed. External finishes are also well advanced with all three surface types under way. The photos below give some sense of the progress to date. We expect completion by the 20th December and our first guests by the 5th January 2009.

Above: View of the southern Level 3 corridor


Above: One of the apartment shared kitchens nearing completion

Above: Services being installed on the roof with the city skyline in the distance

Share/Bookmark

No comments: