The structure itself is up to the 6th floor with both the 6A and 6B slab floors due to be poured next week. Rain has disrupted things this week a little but hopefully this will still occur next week. The complete structure is due for completion by mid July (about 6 weeks).
Work on the marketing of the Village is also well progressed with a new website to be launched in a few weeks and promotional work already occurring. Applications are coming in and some places have been offered. I am now beginning to think through the specifics of the pastoral care and academic support that will need to be in place by January.

Above - Looking out to the inner courtyard from the Level 3 south-west common room

Above - Walls going in on Level 3

Left - Walls and insulation going in on Level 1