
* The new roadway that provides access to Western Campus as well as our basement will be opened today at 5.00pm
* The stormwater retention tank has been completed (this big hole will capture overflow water from our stormwater tanks in extreme weather events and allow it to enter the aquifer)
* The walls on three sides of the basement are virtually complete (and the last one will be done soon)
* The lift pits and stairways to the ground floor have been poured
* The crane based (a 3o cubic metre block of concrete sitting on 4 deep piles) has been completed ready for the crane to be erected in January
The project is a little behind in terms of key limestones (perhaps by a week) but Lipman is hopeful that this can be caught up. Wet weather is always a risk but in spite of one of our wettest Novembers on record there has been minimal disruption at this stage.

